BIG DIG REVIEW TO TARGET COST OVERRUNS
Author(s): Sean Murphy, Globe
Staff
Date:
November 23, 2002
Page: A1
Section:
Metro/Region
The Big Dig's
top official yesterday agreed to work with the state Inspector
General's office in a comprehensive review of the $14.6 billion
Central Artery/Tunnel Project, with an eye toward recouping from
contractors some portion of the billions of dollars in cost overruns
rung up on the project so far.
One of the
prime objectives of the planned review will be to determine whether
the private-sector project manager, Bechtel/Parsons Brinckerhoff,
which has received more than $1 billion in fees, made mistakes for
which the state should be reimbursed. Inspector General Greg Sullivan,
whose office has tracked Big Dig costs for several years, asked in a
letter dated Thursday for the cooperation of Matthew Amorello,
chairman of the Massachusetts Turnpike Authority, which oversees the
project.
"This office
intends to work with the Turnpike Authority to conduct a top-to-bottom
review," Sullivan said yesterday. "For the benefit of taxpayers, this
needs to be done."
Sullivan said
he had not received a personal reply from Amorello, who is a relative
newcomer to the Big Dig, having ascended to the position of chairman
in February. But in an interview late yesterday, Amorello said he was
willing to undertake the review with Sullivan's office.
"We're at the
final stages of this long project and it's appropriate to now get
geared up to take a close look at the state's potential to recover any
costs," he said.
Amorello said
he expected to meet with Sullivan soon to formalize an approach. He
said the Inspector General's office has the advantage of subpoena
power, which means it can compel the release of documents from private
companies, such as Bechtel.
Amorello
declined to comment on specific potential issues with Bechtel, but
Sullivan, in his letter, said, "Based on anecdotal evidence, I believe
that there is a genuine potential for monetary recovery."
In recent
weeks, Amorello said, Turnpike lawyers assigned to the project have
begun sorting through the massive paperwork covering the 15-year-old
project to evaluate Bechtel's performance.
Besides Bechtel,
Amorello and Sullivan say they will scrutinize the performance of
other contractors, including two dozen design firms hired at a cost of
$1 billion to do the project's final design.
The state,
meanwhile, is already engaged in negotiations with construction
contractors over what share of cost overruns are the responsibility of
the construction contractors.
The project's
price has risen from $10.8 billion in 2000 to $14.6 billion today.
Andrew Paven, a
spokesman for Bechtel, declined to address the company's position on
whether it owes the state anything. "There is a contractual process
for looking at these things and we have said we will never shrink from
our responsibilities," he said.
At stake is
millions of dollars in potential savings for state taxpayers. The
federal government in 2000 reacted to the latest in a series of cost
escalations by saying it would cut off further funding of the project,
leaving the state taxpayers to finance at least $6 billion of the
project on their own.
In 2000, the
Inspector General's office released a report critical of the project's
performance in holding contractors accountable for mistakes.
"Although the
project is winding down, nearly 70 percent of project costs are still
within the statute of limitations for possible legal action regarding
cost recovery," Sullivan wrote in Thursday's letter. "This opportunity
must be acted on expeditiously.
"The
commonwealth should not unfairly bear the costs and the blame for all
the project's monetary problems," the letter said.
Sullivan said
such a review would take about a year, and require the hiring of
expert consultants in law, engineering, and construction. He said the
cost of the review would be the Turnpike Authority's.
|