|
Report predicts Big Dig's tunnels won't open on
time
By Raphael Lewis, Globe Staff
September 13, 2002
The
much-anticipated opening of the Big Dig's downtown tunnels will
occur more than two months later than project officials have
stated, but the delays will not increase the project's $14.6
billion price tag, according to a confidential report obtained
yesterday.
The
independent review of the Central Artery's finances and schedule
also found that as much as $108 million in potential savings at
the project will likely be spent to pay rising contractors'
claims.
The
review, commissioned by the state Office of Administration and
Finance, was conducted by Deloitte & Touche, a major auditing
firm that has periodiocally scrutinized the Big Dig's finances
and schedules.
The
report comes as the Big Dig has been trying to gain the public's
confidence following years of skyrocketing costs and repeated
delays. This year the Big Dig has drawn huge crowds to major
portions of the project - the Leonard P. Zakim Bunker Hill
Bridge and the massive underground northbound lanes - and has
raised anticipation that the project is close to the finish
line.
Still,
top Big Dig managers said they are committed to meeting their
more optimistic schedule.
Matthew
Amorello, chairman of the Massachusetts Turnpike Authority and
the state's top overseer of the Big Dig, has said repeatedly
that the Turnpike/I-90 portion of the Big Dig will open Nov. 8,
and I-93 northbound will open Dec. 10. Amorello has given the
project a six-week margin of error on opening dates while
staying within the Big Dig's current budget.
But the
report found that those dates are unrealistic, even if the final
construction push goes flawlessly. The reason, the audit states,
is that software glitches and a tunnel leak have delayed the
assembly by Honeywell Technology Solutions Inc. of the high-tech
system responsible for highway air quality, traffic flow, and
security.
While
project schedules call for Jan. 8 as a worst-case date for I-90,
the audit said Jan. 16 is the more probable date, barring more
problems.
For I-93
northbound, the official worst case calls for Feb. 10, but
Deloitte & Touche says it will probably be March 5.
As for
I-93 southbound, which is supposed to open no later than April
10, 2004, according to the project, the audit says that will
probably not happen until May 18, 2004 - if all goes smoothly.
The
auditors calculated the dates based on data from interviews and
documents from Central Artery officials but used different
methods than the project.
Central
Artery project director Michael Lewis yesterday said the
official schedule is still viable.
''We're
getting down to the crunch, we're weeks away from opening the
facility and, yes, we've got a lot of issues to resolve,'' Lewis
said. ''This is a daily work in progress. [But] I have not
developed a new date. ... We are working on solving issues every
day to get as close to our target date as possible.''
Still,
Lewis said that even if the audit's projected dates are correct,
the delays would not affect the Big Dig's budget.
Amorello,
in a statement, said the schedule will hold within the six-week
margin of error.
Lewis
also said he was less concerned about sacrificing potential cost
savings and more focused on opening the roads and ensuring that
there are enough funds to pay for unforeseeable problems.
Lewis
also said software problems experienced earlier this year when
auditors began their review have largely been resolved. But he
said he was uncertain if Honeywell was fulfilling its agreement
to lay 40,000 feet of fiber-optic cable per week on I-90.
The
audit said the rate has been closer to 25,000 feet.
Despite
the potential delays, top aides to Acting Governor Jane Swift
said they were pleased the report found the project's budget
will remain unchanged. They also said a few weeks' delay in a
project in the works for more than a decade is not a major
concern.
''Deloitte & Touche does say the target dates are
unrealistically aggressive but that the cost implications are
completely accounted for,'' said Stephen P. Crosby, Swift's
chief of staff.
But some
critics were not so sure.
''There
is a sense that we're in ribbon-cutting mode, but the state
needs to be focused to ensure that [the project] doesn't explode
beyond the $14.625 billion,'' said state Representative Joseph
Sullivan, cochairman of the Legislature's Joint Transportation
Committee. ''This is a report that should be heeded because the
state is responsible for any additional exposure.''
Even if
the Big Dig does hold to its schedule, the roadways will still
open later than originally promised. A leak on the Fort Point
Channel crossing last year robbed about two months from the
opening of the Turnpike link, which was originally supposed to
occur this month, and from I-93, which was supposed to open next
month.
Kevin
Sullivan, the current administration and finance secretary, said
he will provide the report to the Federal Highway
Administration, which oversees the Big Dig, and to Kenneth Mead,
the US Department of Transportation inspector.
Amorello,
confident in the schedule, has planned public dedication events
for the Zakim Bridge on Oct. 4-6.
Raphael Lewis can be reached at
rlewis@globe.com.
This story ran on page A1 of the
Boston Globe on 9/13/2002.
Home |
About NASHTU |
Press Room |
Membership |
Conference Activities
Legislation
| Member Reports |
Contact Us
National Association of State Highway
and Transportation Unions
455 Capitol Mall, Suite 501
Sacramento, CA 95814
Phone: 916-446-0584| Fax: 916-446-0489
Copyright ©2002 NASHTU.
All rights reserved.
|